Skip to main content

Stock Transfer process - Intra company explained

Stock transfer process

Stock transfer will be of two kinds:

1. Intra company
2. Inter company 

Intra Company process

If business requires transaction to be performed between two different plants of same company code. Then this considered as intra company transaction in SAP .Hence no billing document will be generated and if required proforma invoice will be raised.

Pre-requisites

1.       Supplying plant and receiving plant need to be created for the same company code
2.       Receiving sales line should be extended to supplying and receiving plant
3.       Supplying plant need to be maintained in supplying sales line
4.       Create customer in supplying sales area
5.       Shipping data need to be maintained for both supplying and receiving plant
6.       During shipping data maintenance customer need to be assigned to receiving sales area
7.       Supplying plant need to be assigned to Delivery type ‘NL’ and purchase document type ‘UB’
8.       Purchasing document type ‘UB’ need to be assigned to the combination of supplying and receiving plant
9.       One step or Two step process need to enabled at the combination of supplying and receiving plant
10.   Shipping point determination need to be done for both supplying and receiving plant
11.   Storage location determination need to be done for both supplying and receiving plant
12.   Material need to be extended to both plants

Business process flow:

1.       Create  Stock transfer Order using ME21N with document type ‘UB’
2.       Create Outbound delivery document with reference to Purchase Order using VL10B or VL10D
3.       Perform Picking and Packing using VL02N
4.       Perform Goods issue using VL02N
5.       Display stock in Transit ( Only in case of two-step process) using MB5T
6.       Create proforma Invoice using VF01 against outbound delivery ( If required)
7.       Create GST Outbound Invoice ( Applicable only in India)
8.       Perform Goods receipt using MIGO ( Only in case of two-step process)
9.       Upon completion of Goods Receipt stock in transit will be disappeared
10.   Create  GST Inbound Invoice document via Code   ‘J_1IG_INV’ ( Applicable only in India)

Movement types used:

Intra Company Transfer:  
One Step - 647

Two step - 641

Comments

Popular posts from this blog

M7021 : Deficit of stock relevant error message during Material Document Cancellation

Issue : When posting a Cancellation for a Material Document in transaction MIGO, you see error 'M7021 Deficit of not stock relevant' although the Purchase Order is setup with an Account assignment. Material / Batch is not managed on Stock Level even though material is valuated. Resolution : The issue is due to program bug and require to implement note - 2502183 - Slog: correction for quantity check. This note is applicable for S/4 HANA 1610 (S4CORE 101) and 1709 (S4CORE 102).

Add Custom fields to sales order screen in Additional Tab B - Header

SAP has provided Additional data Tab A and Tab B for the addition of custom fields to the Standard sales order screen. Screens 8309, 8310 are used for header level and 8459,8460 for item level. Prior to this, we are required to append the custom fields of the Sales order sub screen in VBAK or VBAP. Pass Custom field values in PAI of screen 8309 within Chain statement CHAIN. FIELD: VBAK-<Custom Field 1>         VBAK-<Custom Field 2>         VBAK-<Custom Field 3> ENDCHAIN. Thank you.

Determinations in SAP SD

Plant Determination in Sales Order 1st Preference: System fetches Delivering plant from Customer Material Info Record if Plant is not found at this level then system will look into 2nd Preference:   Delivering plant from Customer Master data if Plant is not found at this level then system will look into 3rd Preference : the Delivering plant for Material Master data If business user overwrites Plant at sales document level then this will be given highest preference. Shipping Point Determination Delivering Plant (Based on above conditions) + Shipping Conditions ( Sales Document Type or  Customer Master Data) + Loading Group ( Material Master ) Storage Location Determination Plant + Shipping Point + Storage Conditions ( Material Master )  ( MALA) Plant + Shipping Point + Situation  ( RETA) Route Determination Departure Zone or Country of the Delivering Plant + Destination Zone or Country of the Ship to Party + Shipping Condition from the Customer Master + Transport